Your total project budget goes beyond the AirDome itself and may include foundation, permitting, preparation works, and utility connections. This tool helps you plan those costs.

Project Configuration

Perimeter

360.0 ft

Area

7200.0 ft²

The figures shown are estimates only and provided for planning purposes. Actual costs may vary based on site conditions, local regulations, labor rates, material availability, engineering requirements, and final project scope.

Cost Breakdown

Grade Beam Foundation
$144,000
Permitting & Approvals
$20,000
Site Preparation & Materials
$3,600
Utilities Connections
$72,000
Cranes/Lifts
$3,600
Temporary Workforce
$14,400
HVAC Integration
$19,440
General Contracting Fee
$59,760
Total Estimated Additional Costs$336,800